The Stan Daniels Metis Manor has been in North Glenora as a senior complex. With the completion of the Renaissance Tower in the Quarters east of downtown, many of the Stan Daniels Metis Manor residents moved in, leaving the Metis Manor ready for redevelopment. The Metis Capital Housing Corporation (MCHC) is proposing to use this building as the new facility for its Family Reunification Program.

MCHC held its first information session with the North Glenora Community League on March 19, 2014. A second was held on October 15, 2014. After the first meeting, the community league solicited questions from residents which were then forwarded to the MCHC for response. A small working group of North Glenora residents have met with representatives of MCHC on a number of occasions since the first meeting to facilitate communication between the North Glenora community and MCHC.  Please give any feedback you have on the proposed project to ngcl.plan@gmail.com.

The following is a list of documents and events relating to the Stan Daniels Metis Manor redevelopment.

Date

Description

March 3, 2016 Jena Properties has bought the property.
April 27, 2015 In December of 2014 the Holmes Group announced that they were no longer involved in the project, at the request of MCHC. The MCHC confirmed to NGCL that, pending the announcement of a new MCHC CEO (at this point still pending), that the development would be on hold. MCHC has committed to monitoring and maintaining the Stan Daniels building while the project is on hold.

NGCL has communicated to MCHC that it is our expectation that the Community Engagement process that had been set in place in 2014 would continue once the new CEO was in place.

April 7, 2015 The project is on hold until further notice, but the Development permit is still underway.
January 20, 2015 Status update
November 16, 2014 Stan Daniels Metis Manor Survey
November 16, 2014 7:00-9:30 North Glenora Community Meeting about Stan Daniels Redevelopment for Residents and Owners Only at North Glenora Community Hall
November 13, 2014 Proposed Variances
November 6, 2014 Development Application submitted. To find it yourself, click on City of Edmonton SLIM Maps and type in the following criteria:

Field Value
I’m looking for Development Applications
Date From: 11/06/2014
To: 11/07/2014
Within Area: North Glenora
Street: 109A AVENUE NW
Application Type: Major Development
November 5, 2014 Real Property Report
November 5, 2014 Geotechnical Report
November 4, 2014 Asbestos Assessment
November 4, 2014 Family Reunification Program Q&A UPDATED Original
October 15, 2014 Second Community Information Session at Westmount Presbyterian Church
September 17, 2014 Information update
September 12, 2014 Milestone Schedule
September 11, 2014 working group: Review of MCHC response to the Community Questions
May 28, 2014 working group: Preliminary review of MCHC response to the Community Questions
May 14, 2014 Concerns of Immediate Neighbours
April 29, 2014 working group: Meeting Minutes
April 24, 2014 Community Questions
April 8, 2014 working group: Meeting Minutes
March 9, 2014 First Community Information Session at North Glenora Community Hall